HDD installation methodology; cleaning the bore - Part 1

This is the first blog in our deliver better outcomes series.

Horizontal Directional Drilling is a common and popular method for installing underground infrastructure. Like all civil engineering methodologies, a scientific approach will reduce risk and increase certainty for the contractor and asset owner.

 
Blick-Cleaning-the-bore.jpg
 

An HDD installation requires the contractor to progress through a number of stages (pilot, reaming and pipeline pullback), completing each step effectively to ensure the following stage can be completed. The steps are interrelated; challenges or poor procedures on one stage influence the following phase, and then may require alterations to the methodology to maximise success.

First, let’s look at project design, fluid design and the pilot phase.
Part 2 dives into reaming and pipe pull.

Project design

The design has a strong influence on the overall risk and cost of the project. A design which takes into account borehole length, depth, inclination angle, hole geometry, geology and rig capability is essential for a successful HDD installation.

Access to accurate relevant geotechnical data can improve the design substantially. This assists the HDD contractor with tooling selection, fluid properties, and drilling parameters, producing cuttings that can be efficiently removed from the borehole with reduced risk of hydro-fracture. Hydro-fracture, or “frac out,” occurs when drilling fluids escape from the borehole to the surface.

During the design phase, a qualified drilling engineer can provide valuable input, potentially reducing risk and providing a design that is easier and simpler to install. This can include using virtual hydraulics software to conduct a hydrofracture analysis, which can benefit the overall design, potentially lengthen shots, and provide greater security in waterways and sensitive area crossings. 

Fluid design

The value that an effective drilling fluid brings to the job cannot be overestimated. Drilling fluid has a number of roles to play. These include transmission of hydraulic energy to the bit, lubrication and cooling, stabilisation of the borehole, and transporting cuttings out of the borehole. 

One key role fluids play is maintaining cuttings in suspension during rod changes and when the pumps are turned off. Inadequate cutting suspension leads to cutting bed development, annular pack, and an increased risk of hydro fracture or stuck pipe. Here, the key is optimising the static gel structure formation, or the ability to gel and suspend cuttings, when flow ceases rapidly. The fluid's ability to rapidly gel when flow ceases is determined using a rotational viscometer.

An effective fluid will be designed to take into account the challenges provided by the design; 

  • a long installation length requiring extended cuttings transport time

  • significant grade changes “dog-legs”

  • changes in bore geometry resulting in flow velocity fluctuations 

  • the size and concentration of the cuttings produced by the tooling and fluid jet impact force.

To effectively transport cuttings, the HDD contractor must balance the drilling advance rate, pump flow rate and the fluid’s dynamic Yield Point and low shear rate viscosity determined using a rotational viscometer. 

Finally, drilling fluid allows the contractor to stabilise the borehole by applying pressure to the borehole walls and creating a filter cake that controls the flow of water across the borehole wall from the annular region. This control of water across the borehole wall is the primary tool for maintaining borehole stability. The biggest cause of instability is water crossing into the formation and destabilising it. Here, the key is the fluid’s ability to form a low-permeability filter cake, which is evaluated using an API filter press.

The larger and more critical the bore, the more sophisticated the fluid design and management needs to be in both planning and executing the installation. In large-scale designs, early engagement with a qualified fluid engineer will provide valuable insight into drilling fluid design and drilling parameters required to provide an efficient hole-cleaning function.

The Pilot Phase

The pilot phase of the HDD process is often overlooked in importance, but it is critical to the success of the following reaming and pipe pull stages. Errors or bad practices during the pilot hole drilling have significant impacts on the successful reaming and pipeline pullback phases.

The pilot phase will be drilled using the most appropriate tooling for the formation. Access to geotechnical data allows an informed choice over the optimal tooling configuration. In hard ground, a mud motor might be selected, a rock bit for weaker rock formations, or a standard blade in softer soil and sands. 

Drilling mud is pumped at prescribed volumes to remove the cuttings from the bore as the formation is cut by the drill bit. During this time, the newly established bore is at the most risk. The relatively narrow annulus created means that the downhole pressure is at its highest of any of the following stages of the HDD process. 

Suppose this fluid circulating pressure exceeds the formation fracture pressure. In that case, micro fractures will occur, allowing fluid to escape into the formation and potentially to the surface, causing infrastructure and environmental damage. The hole-cleaning function is heavily influenced by angular velocity. Still, flow rates are also proportional to pressure - so the pump rate must be planned and managed accurately during the pilot phase. Where insufficient fluid pump rates are implemented, the cutting concentration will be increased, and poor transportation will result. This can quickly lead to an annular pack-off in the small pilot hole and induce hydro-fracture.

It is key to note that any hydro-fracture event induced in the pilot phase of the HDD process has significant implications for the remainder of the pilot hole and subsequent reaming phase. As fluid carrying the cuttings passes a borehole zone where hydro-fracture has previously occurred, some flow will be lost into the fracture. This results in a drop in annular velocity and build-up of cuttings at this location. Eventually, full annular pack-off occurs at these zones, resulting in full mud flow into the fracture, which often presents at the surface. This also increases the chance of a stuck pipe. 

The correctly designed drilling fluid, optimised for the specific borehole design, rig capabilities, tooling, and methodology, will result in good cuttings transportation from the borehole during the pilot phase and significantly increase the likelihood of a successful HDD installation. 

Whilst a hydrofracture is typically caused by damage to the formation in the pilot phase, it may only become evident during the ream (a lower-pressure process with higher volumes passing the damaged area). A hydrofracture is most effectively healed during the pilot phase, where lost circulation materials can be applied most accurately to the damaged area. It is normally possible to treat a hydro fracture discovered during the pilot phase, however specialised technical support is required to manage the process.

Once the pilot bore has been successfully installed, and drilling fluids have circulated back to the rig, the reaming phase begins. 

Part 2

In HDD installation methodology: cleaning the bore—Part 2, we dive into reaming and pipe pull. Our team is available if you have any questions about project design, fluid design, or the pilot phase. We work closely with councilsengineers, and contractors on all stages of the design and installation process. Give our Australia team a call on 03 9068 5688 or our New Zealand team on 07 849 2366.

Clay Adams

Bits, (mountain) biking, and banter. Clay can talk about drilling fluids all day long. 

Clay serves the North Island markets as our Technical Sales Manager. Clay leads the business's construction and tunnelling side and focuses on HDD, waterwell and geotech.

He likes to understand how things work, thinks about the bigger picture, and loves producing great results.

If he’s not on-site, you’ll find him catching a wave or up a mountain.

Previous
Previous

HDD installation methodology; cleaning the bore - Part 2

Next
Next

Are you buying coring consumables from your competition?